Filters
Question type

Study Flashcards

Independent demand is the demand for ______________.


A) finished products
B) subassemblies
C) parts
D) raw materials
E) components

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The ____________ file lists the materials needed to build a product.


A) master production schedule
B) bill of material
C) inventory records
D) material needs
E) build structure

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

The three criteria for selecting an ERP system include _____________,________________,and _______________.

Correct Answer

verifed

verified

functionality,ease o...

View Answer

Which of the following is not true for planned orders?


A) They are necessary only for finished products.
B) They result when there is not enough inventory to cover the gross requirements.
C) The quantity is calculated using the lot-sizing rule.
D) The lead time is required to determine when the order should be placed.
E) The inventory records file is updated for the order.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Gross requirements for finished products are taken from ________________________.


A) the inventory records file
B) the order entry file
C) the authorized MPS
D) the bill of materials file
E) forecasted sales

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

If setup costs are essentially zero (negligible when compared to carrying costs) ,which approach should be used for lot sizing?


A) lot for lot
B) fixed order quantity
C) period order quantity with POQ = 6 periods
D) period order quantity with POQ = 2 periods
E) period order quantity with POQ = 4 periods

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Which ERP module includes work-flow analysis?


A) finance and accounting
B) information systems
C) sales and marketing
D) production and materials management
E) human resources

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

When there is insufficient inventory to satisfy the forecast for a particular period a(n) _____________ order must be placed.


A) BOM
B) restock
C) inventory request
D) MPS
E) MRP

F) D) and E)
G) None of the above

Correct Answer

verifed

verified

_______________ MRP is an MRP system that includes production planning,master production scheduling,and capacity requirements planning.


A) Fully-integrated
B) Closed-loop
C) Open-loop
D) Wide-range
E) Enterprise

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

In the mid-1970s,MRPII was developed.One of its major components is:


A) leadership
B) inventory management
C) operations execution
D) strategic management
E) marketing

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

MRP systems require ______________________,______________________,and ______________________ as inputs.

Correct Answer

verifed

verified

bill of materials,au...

View Answer

Production and inventory planners release orders to ________________________.


A) the expediter
B) either an external supplier or to the shop floor
C) the logistics manager
D) either the shop floor or to the warehouse
E) marketing

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Given the following data: The beginning inventory is 0 and there are no scheduled receipts.The order cost is $90 and the holding cost is $1 per part per period. (a)What are the order costs,carrying costs,and totals cost over the 9 periods using the lot-for-lot size rule? (b)What are the order costs,carrying costs,and totals cost over the 9 periods using the fixed order quantity rule with FOQ = 100? (c)What are the order costs,carrying costs,and totals cost over the 9 periods using the period order quantity rule with POQ = 3?

Correct Answer

verifed

verified

(a)order costs = $810,carrying costs = $...

View Answer

Gross requirements for finished products are taken from the order entry file.

A) True
B) False

Correct Answer

verifed

verified

Under the lot for lot rule,order sizes are essentially determined directly from gross requirements.

A) True
B) False

Correct Answer

verifed

verified

___________________ uses the planned orders generated by MRP to evaluate the feasibility of long-term or blanket contracts and to determine delivery need.

Correct Answer

verifed

verified

Dell practices _____________________________.


A) focused customization
B) make to stock production
C) mass merchandising
D) mass customization
E) frozen assembly schedules

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Given the following data: (a)What are the workloads for periods 3,4,and 5? (b)There are 168 hours of operating time per machine each period.How many machines should be operated for periods 3,4,and 5?

Correct Answer

verifed

verified

(a)804.7 hours for period 3,1,...

View Answer

Selection of the lot size rule to be used should be based on minimizing ____________________.


A) the order size
B) late shipments
C) total processing time
D) quality problems
E) the sum of ordering and carrying costs

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

The current time period is referred to as __________________.


A) time zero
B) the point of departure
C) the start time
D) the action bucket
E) this year

F) B) and D)
G) C) and E)

Correct Answer

verifed

verified

Showing 101 - 120 of 131

Related Exams

Show Answer